To save content items to your account,
please confirm that you agree to abide by our usage policies.
If this is the first time you use this feature, you will be asked to authorise Cambridge Core to connect with your account.
Find out more about saving content to .
To save content items to your Kindle, first ensure no-reply@cambridge.org
is added to your Approved Personal Document E-mail List under your Personal Document Settings
on the Manage Your Content and Devices page of your Amazon account. Then enter the ‘name’ part
of your Kindle email address below.
Find out more about saving to your Kindle.
Note you can select to save to either the @free.kindle.com or @kindle.com variations.
‘@free.kindle.com’ emails are free but can only be saved to your device when it is connected to wi-fi.
‘@kindle.com’ emails can be delivered even when you are not connected to wi-fi, but note that service fees apply.
Operational roadblocks and organizational delays in multicenter clinical trials have been evident for decades, with the start-up cycle being especially notorious for setbacks. To address these challenges and improve multicenter clinical trial execution, we developed an accelerated start-up (ASU) management strategy – a structured site onboarding approach based on lean management principles.
Methods:
Three elements were integrated into the strategy: a standardized workflow, a dedicated site navigator (SN), and an electronic tracking system. We examined the range, central tendencies, and distribution of site activation times among differing combinations of these three elements. To determine how these combinations affected individual start-up milestones, we fit mixed models to compare percent achievement of predetermined milestone benchmarks and time to completion.
Results:
Thirteen consecutive trials (n = 308 site activations) employed three distinct combinations of the three ASU elements. Trials using all three elements (n = 6) had 160 total site activations in a median of 133 days. Three trials without the SN element had 52 total site activations in a median of 191 days. Four trials without the standardized workflow element had 96 total site activations in a median of 277 days. Significant differences between combinations included times to sIRB submission (p = 0.004), training/certificates completion (p = 0.03), and site activation (p = 0.003). Results suggest sites activated faster and achieved predetermined benchmarks for every milestone more often when three elements were employed.
Conclusion:
This sample trial start-up data supports that sites can meet ambitious timelines, underscoring the strategy’s potential to streamline workflows and improve site team performance.