Chapter 16 - Coping with Changes to the Plan

Dealing with Twists and Turns in Projects

from Part III - Practical Tips

Published online by Cambridge University Press:  aN Invalid Date NaN

Lavagnon A. Ika
Affiliation:
University of Ottawa
Jeffrey K. Pinto
Affiliation:
Pennsylvania State University
Get access

Summary

To investigate project behaviour, and to better understand it from the perspective of a practitioner, I undertake an ethnographic study of the construction of a house in India that I was recently involved with. I find that the project evolved through three distinct phases – the teething troubles phase, the honeymoon phase and the nightmare phase – each of which displayed distinct behaviours. Using both quantitative and qualitative analysis of observational data, this chapter attempts to describe the evolution of the project through these phases and their inherent internal dynamics. In doing so I provide a micro-perspective on project behaviour, suggestions on how each of these distinct phases can be managed and insights to scholars of project behaviour on how project behaviours is not only fragmented across a project’s lifecycle, but is also perhaps shaped by simultaneously occurring and entangled ‘hands’ or guiding forces. This chapter adds to the debate on whether observed project behaviour that often leads to mis-performance is the result of unwitting or malignant influences.

Information

Type
Chapter
Information
Publisher: Cambridge University Press
Print publication year: 2025

Access options

Get access to the full version of this content by using one of the access options below. (Log in options will check for institutional or personal access. Content may require purchase if you do not have access.)

Book purchase

Temporarily unavailable

References

Ahiaga-Dagbui, D. D, and Smith, S. D. (2014) Rethinking construction cost overruns: Cognition, learning and estimation. Journal of Financial Management and Property Construction, 19(1), 3854.10.1108/JFMPC-06-2013-0027CrossRefGoogle Scholar
Alshihri, S., Al-Gahtani, K., and Almohsen, A. (2022). Risk factors that lead to time and cost overruns of building projects in Saudi Arabia. Buildings, 12(7), 902.10.3390/buildings12070902CrossRefGoogle Scholar
Anheier, H. K. (2016). Of Hiding Hands and other ways of coping with uncertainty: A commentary. Social Research, 83(4), 10051010.10.1353/sor.2016.0064CrossRefGoogle Scholar
Barley, S. R., and Kunda, G. (2001). Bringing work back in. Organization Science, 12(1), 7695.10.1287/orsc.12.1.76.10122CrossRefGoogle Scholar
Choo, H. J., and Tommelein, I. D. (1999). Parade of trades: A game for understanding variability and dependence. Construction Engineering and Management Program, Civil and Environmental Engineering Department. University of California, Berkeley.Google Scholar
De Neufville, R., and Scholtes, S. (2011). Flexibility in engineering design. MIT Press.10.7551/mitpress/8292.001.0001CrossRefGoogle Scholar
Eden, C., Williams, T., Ackermann, F., and Howick, S. (2000). The role of feedback dynamics in disruption and delay on the nature of disruption and delay (D&D) in major projects. Journal of the Operational Research Society, 51(3), 291300.10.1057/palgrave.jors.2600919CrossRefGoogle Scholar
Eden, C., Ackermann, F., and Williams, T. (2005). The amoebic growth of project costs. Project Management Journal, 36(2), 1527.10.1177/875697280503600203CrossRefGoogle Scholar
Flyvbjerg, B., Holm, M., and Buhl, S. (2002). Underestimating costs in public works projects. Journal of the American Planning Association, 68(3), 279295.10.1080/01944360208976273CrossRefGoogle Scholar
Flyvbjerg, B., Bruzelius, N., and Rothengatter, W. (2003). Megaprojects and risk: An anatomy of ambition. Cambridge University Press.10.1017/CBO9781107050891CrossRefGoogle Scholar
Flyvbjerg, B. (2016). The fallacy of beneficial ignorance: A test of Hirschman’s Hiding Hand. World Development, 84, 176189.10.1016/j.worlddev.2016.03.012CrossRefGoogle Scholar
Flyvbjerg, B., and Sunstein, C. R. (2016). The principle of the malevolent hiding hand; or, the planning fallacy writ large. Social Research: An International Quarterly, 83(3), 9791004.10.1353/sor.2016.0063CrossRefGoogle Scholar
Flyvbjerg, B., Ansar, A., Budzier, A., Buhl, S., Cantarelli, C., Garbuio, M., Glenting, C., Holm, M. S., Lovallo, D., Lunn, D., Molin, E., Rønnest, A., Stewart, A., and Van Wee, B. (2018). Five things you should know about cost overrun. Transportation Research Part A: Policy and Practice, 118, 174190.Google Scholar
Gil, N., and Pinto, J. (2018). Polycentric organizing and performance: A contingency model and evidence from megaproject planning in the UK. Research Policy, 47(4), 717734.10.1016/j.respol.2018.02.001CrossRefGoogle Scholar
Grabher, G. (2004). Temporary architectures of learning: Knowledge governance in project ecologies. Organization Studies, 25(9), 14911514.10.1177/0170840604047996CrossRefGoogle Scholar
Henisz, W. J., Levitt, R. E., and Scott, W. R. (2012). Toward a unified theory of project governance: Economic, sociological and psychological supports for relational contracting. Engineering Project Organization Journal, 2(1–2), 3755.10.1080/21573727.2011.637552CrossRefGoogle Scholar
Hirschman, A. O. (1967). Development projects observed. Brookings Institution.Google Scholar
Ika, L. A., Love, P. E. D., and Pinto, J. K. (2022). Moving beyond the Planning Fallacy: The emergence of a new principle of project nehavior. IEEE Transactions on Engineering Management, 69(6), 33103325.10.1109/TEM.2020.3040526CrossRefGoogle Scholar
Ika, L. A., Pinto, J. K., Love, P. E. D., and Pache, G. (2023). Bias versus error: Why projects fall short. Journal of Business Strategy, 44(2), 6775 10.1108/JBS-11-2021-0190CrossRefGoogle Scholar
Jones, L. R., and Euske, K. J. (1991). Strategic misrepresentation in budgeting. Journal of Public Administration Research and Theory, 1(4), 437460.Google Scholar
Kahneman, D. (2017). Thinking, fast and slow. Farrar, Straus and Giroux.Google Scholar
Kahneman, D., andTversky, A. (1977). Intuitive prediction: Biases and corrective procedures. Defense Advanced Research Projects Agency.Google Scholar
Koskela, L., Howell, G., Ballard, G., and Tommelein, I. (2002). The foundations of lean construction. Design and Construction: Building in Value, 291, 211226.Google Scholar
Koushki, P. A., and Kartam, N. (2004). Impact of construction materials on project time and cost in Kuwait. Engineering, Construction and Architectural Management, 11(2), 126132.10.1108/09699980410527867CrossRefGoogle Scholar
Kunz, J., and Fischer, M. (2020). Virtual design and construction. Construction Management and Economics, 38(4), 355363.10.1080/01446193.2020.1714068CrossRefGoogle Scholar
Love, P. E. D, and Ahiaga-Dagbui, D. (2018). Debunking fake news in a post-truth era: The plausible untruths of cost underestimation in transport infrastructure projects. Transportation Research Part A: Policy and Practice, 113, 357368.Google Scholar
Love, P. E. D., Pinto, J. K., and Ika, L. A. (2022). Hundreds of years of pain, with minimal gain: Capital project cost overruns, the past, present, and optimistic future. IEEE Engineering Management Review, 50(4), 5670.10.1109/EMR.2022.3219362CrossRefGoogle Scholar
Love, P. E. D., and Ika, L. A. (2022). Making sense of hospital project misperformance: Over budget, late, time and time again—Why? And what can be done about it? Engineering, 12, 183201.10.1016/j.eng.2021.10.012CrossRefGoogle Scholar
Love, P. E. D., Ika, L. A., and Sing, M. C. (2019). Does the planning fallacy prevail in social infrastructure projects? Empirical evidence and competing explanations. IEEE Transactions on Engineering Management, 69(6), 25882602.10.1109/TEM.2019.2944161CrossRefGoogle Scholar
Love, P. E. D., Sing, M. C. P., Ika, L.A., and Newton, S. (2019). The cost performance of transportation projects: The fallacy of the Planning Fallacy account. Transportation Research Part A: Policy and Practice, 122, 120.Google Scholar
Mak, S., and Raftery, J. (1992). Risk attitude and systematic bias in estimating and forecasting. Construction Management and Economics, 10(4), 303320.10.1080/01446199200000028CrossRefGoogle Scholar
Meng, X. (2012). The effect of relationship management on project performance in construction. International Journal of Project Management, 30(2), 188198.10.1016/j.ijproman.2011.04.002CrossRefGoogle Scholar
Miller, R., and Lessard, D. R. (2001). The strategic management of large engineering projects: Shaping institutions, risks, and governance. MIT Press.10.7551/mitpress/6478.001.0001CrossRefGoogle Scholar
Ninan, J., Mahalingam, A., and Clegg, S. (2019). External stakeholder management strategies and resources in megaprojects: an organizational power perspective. Project Management Journal, 50(6), 625640.10.1177/8756972819847045CrossRefGoogle Scholar
Oswald, D., and Dainty, A. (2020). Ethnographic research in the construction industry: A critical review. Journal of Construction Engineering and Management, 146(10), 113.10.1061/(ASCE)CO.1943-7862.0001917CrossRefGoogle Scholar
Pink, S., Tutt, D., Dainty, A., and Gibb, A. (2010). Ethnographic methodologies for construction research: Knowing, practice and interventions. Building Research Information, 38(6), 647659.10.1080/09613218.2010.512193CrossRefGoogle Scholar
Rosenfield, Y. (2014). Root-cause analysis of construction-cost overruns. ASCE Journal of Construction Management, 140(1). DOI: 10.1061/(ASCE)CO.1943-7862.0000789.Google Scholar
Shehu, Z., Endut, I. R., Akintoye, A., and Holt, G. (2014). Cost overrun in the Malaysian construction industry projects: A deeper insight. International Journal of Project Management, 32(8), 14711480.10.1016/j.ijproman.2014.04.004CrossRefGoogle Scholar
Subramani, T., Sruthi, P. S., and Kavitha, M. (2014). Causes of cost overrun in construction. IOSR Journal of Engineering, 4(6), 17.10.9790/3021-04640107CrossRefGoogle Scholar
Taha, G., Sherif, A., and Badawy, M. (2022). Dynamic modeling for analyzing cost overrun risks in residential projects. ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering, 8(3). DOI: 10.1061/AJRUA6.0001262.Google Scholar
Thomsen, J., Levitt, R. E., and Nass, C. I. (2005). The virtual team alliance (VTA): Extending Galbraith’s information-processing model to account for goal incongruency. Computational & Mathematical Organization Theory, 10(4), 349372.10.1007/s10588-005-6286-yCrossRefGoogle Scholar
Williams, T., Eden, C., Ackermann, F., and Tait, A. (1995). The effects of design changes and delays on project costs. Journal of the Operational Research Society, 46, 809818.10.1057/jors.1995.114CrossRefGoogle Scholar

Accessibility standard: WCAG 2.0 A

Why this information is here

This section outlines the accessibility features of this content - including support for screen readers, full keyboard navigation and high-contrast display options. This may not be relevant for you.

Accessibility Information

The PDF of this book conforms to version 2.0 of the Web Content Accessibility Guidelines (WCAG), ensuring core accessibility principles are addressed and meets the basic (A) level of WCAG compliance, addressing essential accessibility barriers.

Content Navigation

Table of contents navigation
Allows you to navigate directly to chapters, sections, or non‐text items through a linked table of contents, reducing the need for extensive scrolling.
Index navigation
Provides an interactive index, letting you go straight to where a term or subject appears in the text without manual searching.

Reading Order & Textual Equivalents

Single logical reading order
You will encounter all content (including footnotes, captions, etc.) in a clear, sequential flow, making it easier to follow with assistive tools like screen readers.
Short alternative textual descriptions
You get concise descriptions (for images, charts, or media clips), ensuring you do not miss crucial information when visual or audio elements are not accessible.
Full alternative textual descriptions
You get more than just short alt text: you have comprehensive text equivalents, transcripts, captions, or audio descriptions for substantial non‐text content, which is especially helpful for complex visuals or multimedia.
Visualised data also available as non-graphical data
You can access graphs or charts in a text or tabular format, so you are not excluded if you cannot process visual displays.

Visual Accessibility

Use of colour is not sole means of conveying information
You will still understand key ideas or prompts without relying solely on colour, which is especially helpful if you have colour vision deficiencies.
Use of high contrast between text and background colour
You benefit from high‐contrast text, which improves legibility if you have low vision or if you are reading in less‐than‐ideal lighting conditions.

Save book to Kindle

To save this book to your Kindle, first ensure no-reply@cambridge.org is added to your Approved Personal Document E-mail List under your Personal Document Settings on the Manage Your Content and Devices page of your Amazon account. Then enter the ‘name’ part of your Kindle email address below. Find out more about saving to your Kindle.

Note you can select to save to either the @free.kindle.com or @kindle.com variations. ‘@free.kindle.com’ emails are free but can only be saved to your device when it is connected to wi-fi. ‘@kindle.com’ emails can be delivered even when you are not connected to wi-fi, but note that service fees apply.

Find out more about the Kindle Personal Document Service.

Available formats
×

Save book to Dropbox

To save content items to your account, please confirm that you agree to abide by our usage policies. If this is the first time you use this feature, you will be asked to authorise Cambridge Core to connect with your account. Find out more about saving content to Dropbox.

Available formats
×

Save book to Google Drive

To save content items to your account, please confirm that you agree to abide by our usage policies. If this is the first time you use this feature, you will be asked to authorise Cambridge Core to connect with your account. Find out more about saving content to Google Drive.

Available formats
×